Equipment and operating figures

Figures describe the configuration and operating conditions in this case.

Platform
2200 Series low-profile belt conveyor
Dimensions
20 feet long × 15 inches wide
Operating speed range in this process
About 3 feet/minute down to 3 feet/10 minutes
Work cells
5
Reported team size
4–5 people
Reported production value
US$2.5 million increasing to US$10 million with the same team
Further target
US$20 million; a future goal, not an achieved result

The process sequence

  1. Set the product-specific pace
  2. Load the actuator
  3. Add components at five work cells
  4. Complete the assembly

Expanding the building or improving the assembly method

The producer made programmable electric actuators based on moving-coil technology. After several years of growth of roughly thirty percent annually, it considered either adding building space or making production leaner within the existing facility.

The chosen approach was to improve the assembly process. A low-profile belt conveyor, introduced into the operation in late 2014, became a moving assembly line linking five miniature work-station cells. Components could be added progressively as the actuator travelled along the belt.

Very slow movement, selected for the product

The conveyor was twenty feet long and fifteen inches wide. Its pace varied considerably with product complexity: about three feet per minute for a simpler assembly, or as little as three feet of travel over ten minutes for more involved work.

This was not a maximum-speed application. The important capability was controlled movement at very low speed, allowing the assembly pace to be set for the work content of a particular product. When the product changed, the pace could change with it rather than forcing every actuator through a single fixed cycle.

Construction and implementation choices

The low profile suited a lightweight industrial assembly task. V-guided belting supported tracking, and the T-slot frame allowed work-cell accessories to be bolted on as the process developed.

The project also had a short implementation schedule. The original account records a three-day lead time for the selected conveyor at that time. The enduring design point is the ability to integrate a specified conveyor into an existing work area with accessory mounting and accurate low-speed movement; the historical lead time is not a current delivery offer.

Reported output and the next improvement target

The owner reported an increase in the value of assembled products from US$2.5 million to US$10 million using the same team of four to five people. That is a production-value comparison for this operation, not a measured fourfold increase in units per hour attributable to the conveyor alone.

Additional tooling cells and further process refinement were being considered, with an ambition to reach US$20 million in product output. More assembly lines were also anticipated. These were future plans in the account and are not presented as completed results.